Kanaka Durga Temple Flyover Status


Recommended Posts

Posted

Subways : 3/3

 
✅

Girders : 30/30

 
✅

Pillars : 55/55

 
✅

Spines : 650+/650+

 
✅

Wings : 1372+/1372+

 
✅

Bhavanipuram Side Ramp :

 
✅

PNBS Side Ramp :

 
❎

Ramp, concrete works, roads & finishing works pending. Expecting opening month June 2020.

Thank You CM Jagan Anna

Posted
14 minutes ago, AndhraneedSCS said:

Central Govt dhi kada. What will Jagan do?

అన్న సెంట్రల్ Govt కాయ కోసి ఫ్లైఓవర్  తెచ్చిండు ... మొత్తం క్రెడిట్ అంతా అన్నదే ....

  • Upvote 1
Posted
20 minutes ago, snoww said:

Matter Leni Soma constructions ki contract ichi inni years delay sepinchukunnaru.

What do you know about soma

Posted
5 hours ago, AndhraneedSCS said:

Central Govt dhi kada. What will Jagan do?

Stay Calm and give credit to Anna

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...